III.2: Permit application characteristics
An applicant must comply with the following:
a) Applicant should submit filled right of way form provided in Appendix1 of these
guidelines;
b) The demand of permit should be accompanied by the documents listed in design
stages and submissions part;
c) Permit application must be in the name of the fiber optic network provider that is
responsible for the installation and maintenance of the cable and the signature of
applicant must appear on permit application;
d) Permit application shall list the name, address, phone number, and emergency 24hours phone number of the contact person for the fiber optic network provider;
Sub-contractor information may be provided separately.
e) Permit application documents should be submitted in soft and hard copy to the
Regulatory Authority office.

III.2.1: Separate Permits Required
Work on the inter-district must be submitted on separate permit applications, and the
expected date of permits intersection work is to be determined.

III.2.2: Works Notification
The list of routes/street names/locations where the work is to be conducted will be
communicated to other utilities providers by the Regulatory Authority. Comments from
concerned utilities providers will be provided within ten(10) days from the date of the
reception of works notification.

III.2.3: Limitations
Permit will be issued for applications on any exceeding distance. It is prohibited to conduct