E. RDB/ENVIRONMENTAL COMPLIANCE will subject the application to
applicable environmental management procedures. This can be done
concurrently with application to LA. RDB/ENVIRONMENTAL COMPLIANCE
checks to ensure that project coordinates and site details match those
contained in letter of no objection from RURA and undertakes necessary
consultations with relevant parties and thereafter grant/deny clearance.
F. Upon receipt of the two (2) approvals from LA and RDB/ENVIRONMENTAL
COMPLIANCE, RURA issues final permit to build the site and install
communication infrastructure.