Appendix5. Summary of Values Recommended by These Guidelines
No Item

Value

1

Excavation and backfilling duration

≤3days

2

Excavation notification to the other utilities ≥ 5 days before commencement
operators

3

Distance of cable from the edge of shoulder

1.5m

4

Minimum distance of the cable from the off
of roadway

2.5metres

5

Interval distance between FOC and existing 1m
underground infrastructure

6

Trench depth

≥80cm

7

Trench depth while road crossing

≥1meter

8

Visible tape along the trenches below 30 cm
ground surface.

9

Interval distance between two visible tape 300m to 500m
marker indicating cable route

10

Distance of Manhole/Hand hole from the 2metres
edge of shoulder

11

Minimum distance of the Manhole/Hand
hole from the off of roadway

3m

12

Accomplishment report submission

≤5 working days from
mentioned on the schedule

13

As-built documentation report submission

≤30 working days from the date
mentioned on the schedule

14

Right of way permit delivery

10 working days

15

Right of way permit validity

3months

18

the

date