Appendix5. Summary of Values Recommended by These Guidelines
No Item
Value
1
Excavation and backfilling duration
≤3days
2
Excavation notification to the other utilities ≥ 5 days before commencement
operators
3
Distance of cable from the edge of shoulder
1.5m
4
Minimum distance of the cable from the off
of roadway
2.5metres
5
Interval distance between FOC and existing 1m
underground infrastructure
6
Trench depth
≥80cm
7
Trench depth while road crossing
≥1meter
8
Visible tape along the trenches below 30 cm
ground surface.
9
Interval distance between two visible tape 300m to 500m
marker indicating cable route
10
Distance of Manhole/Hand hole from the 2metres
edge of shoulder
11
Minimum distance of the Manhole/Hand
hole from the off of roadway
3m
12
Accomplishment report submission
≤5 working days from
mentioned on the schedule
13
As-built documentation report submission
≤30 working days from the date
mentioned on the schedule
14
Right of way permit delivery
10 working days
15
Right of way permit validity
3months
18
the
date